Weekly Clean Energy Transformation Act (CETA) Bulletin- September 14

Source: Washington Department of Commerce, September 14, 2020

Announcements

CETA second draft rules comment deadline is today

On Aug. 14, Commerce posted revised draft rules for implementation of the state’s clean electricity law, the Clean Energy Transformation Act (CETA). The second draft rules are available on the CETA rulemaking website. The second draft rules follow multiple stakeholder workshops and written comment opportunities on the agency’s first draft, which was published in April.

Commerce is requesting written comments on the second draft by Sept. 14. Send written comments by email to CETA@commerce.wa.gov. Please submit comments in both Word and PDF formats, if possible.

Four other documents are posted with the second draft rules:

  • A marked-up version of the second draft rules showing changes from the first draft and identifying key stakeholder comments and the response to those comments.
  • A draft guidance document concerning equity-related provisions in CETA and the draft rules. Commerce will be accepting feedback on the draft document. Comments can be sent to Sarah Vorpahl (sarah.vorpahl@commerce.wa.gov).
  • A request for information from electric utilities on cost impacts of the draft rules. Commerce is requesting that utilities submit information on costs by Sept. 25.
  • A response to Washington Public Utility Districts Association’s requests for a substantial legislative rule analysis.

In the marked-up version, Commerce has noted several issues where further comment is invited. These issues, and the stakeholder who raised them, are:

Rule SectionDescription
050Require annual or biennial progress reports (Renewable NW,NW Energy Coalition)
200Simplified CEIP reporting form for small utilities (WPUDA, small utilities)
230More workshops before adopting 2% incremental cost rule (WPUDA)
300No rule on coal-fired resources until Markets Workgroup finishes (Public Generating Pool)
300Prohibit serial purchases of unspecified power, alternative language in subsection (4) (Renewable NW)
320Use of electricity under 80% portion of Greenhouse Gas (GHG) Neutral Standard, section 410 as an alternative approach (Multiple stakeholders)
330Pro rata conservation target for small utilities (WPUDA)
340Different standard for acquisition of generators during an emergency (WPUDA)
350More workshops on use of alternative compliance options for utilities using 2% incremental cost approach (WPUDA)
410Requirements for RECs used to comply with the 80% portion of the GHG Neutral Standard (Multiple stakeholders)

Deadline extended for information cost impacts of the draft rules

At Commerce’s Sept. 2 workshop, stakeholders requested more time to submit information on cost impacts of the draft rules. Commerce has extended the submission deadline to Sept. 25. Responses to Commerce’s request are voluntary. If you have any questions, contact CETA@commerce.wa.gov.

Utility Energy Assistance Program Survey

Commerce’s data survey tool for utility data collection on low-income energy assistance programs is available on the Energy Assistance under CETA webpage. Instructions (both PDF and Word versions) of the survey questions are also available on the webpage. The tool will remain open until Nov. 13. If you have questions about this process or the data tool, please contact Sarah Vorpahl (sarah.vorpahl@commerce.wa.gov).

Upcoming Events and Deadlines

Details on these events are available on the CETA rulemaking webpage.

DateEventTopic
Sept. 14Comment deadlineSecond draft rules and cost impacts
Sept. 25Submission deadlineCost impact request (voluntary)
Oct. 21CR-102 filingTentative date for filing CR-102
Nov. 13Submission deadlineUtility energy assistance program survey
Dec. 2Public hearing and commentsTentative date for public hearing and comments